This example illustrates a simple network activation on a new
jack where the customer makes a request via the help desk.
- customer contacts help desk
- customer gives location info to consultant
- customer gives account info to consultant
- customer gives contact info to consultant
- consultant submits order via web page on behalf of customer
- separate orders must be made for orders across multiple buildings
- help desk is a registered contact for status updates
- customer places marker where jack is to be located
- markers are printed via a web page or placed by consultant
- contacts receive estimated completion time
- transaction is queued for a facility analyst
- queue is ordered by ect and priority
- queue is grouped by like jobs and similar locatons
- process manager monitors queue
- missed ects result in notifications to process manager and contacts
- transaction is accepted by a facility analyst
- contacts receive notification of transaction acceptance, contact information
- jack installation is scheduled automatically with contractor
- facility analyst may change schedules as necessary
- requests in similar locations may be consolidated
- contractor installs and tests jack
- contractor sends monthly bill and testing data to MIT
- CSR reconcile contractor billing with installations performed
- facility analyst receives notification after jack installation
- facility analyst and process manager monitoring for missed ect
- facility analyst activates port
- facility analyst tests port
- facility analyst closes loop with customer and help desk
- facility analyst updates transaction status
- facility analyst records connection information
- feedback solicited on transaction close
- transaction billing info sent to SAP
measures recorded:
- time transaction sat in queue
- time to schedule contractor
- time to complete requested jack installation
- time between jack install and network activation
- jacks installed
- ports activated
- customer satisfaction
- did customer get what they want
- satisfied with staff & contractors
- satisfied with process
- process manager intervention
|